Road Construction: Cogmanskloof road closure

As part of the road construction project between Ashton and Montagu, blasting will occur on Tuesdays and Thursdays for the next 3 to 5 months.  The road through Cogmanskloof will be closed from 11:00 to 13:00 on the days of blasting.

With the intention of providing the safest possible environment, traffic will be prevented from entering Cogmanskloof at 11:00 on the days of blasting. 

The traffic will be stopped on the eastern side of Ashton and on the western side of Montagu.  

Road signs will warn motorists in advance of the road closures.

 

Blasting schedule for the next few months:

Cogmanskloof Blasting Schedule   (March 2018 to May 2018)

Thursday

15 March 2018

Blasting

Tuesday

20 March 2018

Blasting

Thursday

22 March 2018

Blasting

Tuesday

27 March 2018

Blasting

Thursday

29   March 2018

No   blasting - school holidays

Tuesday

03   April 2018

No   blasting - school holidays

Thursday

05   April 2018

No   blasting - school holidays

Tuesday

10 April 2018

Blasting

Thursday

12 April 2018

Blasting

Tuesday

17 April 2018

Blasting

Thursday

19 April 2018

Blasting

Tuesday

24 April 2018

Blasting

Thursday

26 April 2018

No blasting

Tuesday

01   May 2018

No   blasting - public holiday

Thursday

03 May 2018

Blasting

Tuesday

08 May 2018

Blasting

Thursday

10 May 2018

Blasting

Tuesday

15 May 2018

Blasting

Thursday

17 May 2018

Blasting

Future   dates will be confirmed at a later stage.

* This Bulletin is also posted on the website should you need to revisit it : https://www.montagu.org.za/news/upgrading-of-cogmans-pass/#Bulletin40